Copied from a thread started by Tony and updated for 2013:
Pugfest 2013 planning
-360 days Book venue - Done
-300 days Finalise logo / order flyers - Done
-210 days Update Pugfest website with new logo and relevant material - Done (plus new website too)
January
-180 days send out traders invites, Create 1st press release and send
March
-120 days Start advertising magazines / forums - forums done, Book car park attendants – Alex Fleming – 01684 296809
early April
-75 days Tickets live in shop, Send 2nd Press release.
May
-60 days Order merchandise, Order wristbands - Done
June
-30 days Ensure public liability is valid / renew, Get MSA exemption certificate, Finalise traders / request final payment, Print vehicle passes
28 June
-16 days Tickets dispatched
4 July
-10 days Last ticket sales
10 July
- 3 days Get float from bank
13 July
-1 day Put up direction signs, Organise venue
0 days Run the event!:waytogo:pugbanner:rain:
16 July
+2 days All monies banked
19 July
+5 days Thank you letters sent out to traders
21 July
+7 days reports written for magazines and sent